// Module included in the following assemblies:
// * migration_toolkit_for_containers/mtc-migrating-vms.adoc
:_mod-docs-content-type: REFERENCE
[id="mtc-vm-storage-migration-process-works_{context}"]
= About the virtual machine storage migration process
During the migration, a `MigMigration` resource is created indicating what type of migration is happening.
The types of migration are as follows:
* Stage: Stage migration copies data from the source cluster to the target cluster without stopping the application. You can run a stage migration multiple times to reduce the duration of the cutover migration.
* Rollback: Rolls back a completed migration.
* Cutover: Cutover migration stops the transactions on the source cluster and moves the resources to the target cluster.
The status of the `MigMigration` resource contains progress information about any live storage migrations.
Any offline migrations contain the `DirectVolumeMigrationProgress` status that shows the progress of the offline migration.
Each `MigMigration` creates a `DirectVolumeMigration` if the migration plan is a direct volume migration plan.
To perform a storage live migration, a direct volume migration is required.